Rivelle's timeline from launch to TOP and MOP: what owners and future buyers should know
Written by Jeffery Ng · Published · 6 min read
An EC has a long life before it becomes a normal condo. Here is Rivelle's timeline stage by stage, from progress payments during construction to key collection, the defects inspection, the five-year minimum occupation period and the resale windows that open in 2035 and 2040.

Buying an executive condominium from the developer starts a clock that runs for ten years. The dates on the Sale and Purchase Agreement set the first part; the EC rules set the rest. For Rivelle, the two contractual dates are an expected vacant possession date of 30 June 2030 and an expected legal completion date of 30 June 2033. Everything else follows from the first of those.
This article lays out the stages in order, what happens at each, and what an owner or a prospective buyer should do. Where a date is contractual it is stated as such; where it is an estimate it is marked.
Stage 1: Launch and booking (March to April 2026)
Preview opened on 6 March 2026; booking day was 21 March. Buyers paid a 5 percent booking fee and received an Option to Purchase. The remaining units sold at a second ballot in April, after which the sales gallery closed (launch figures to be confirmed against the developer's sales update).
What buyers did: chose between the Normal Payment Scheme (5 percent cash at booking, 15 percent on exercise, 80 percent progressively) and the Deferred Payment Scheme (20 percent upfront, 80 percent at TOP, at a premium of about 2 to 3 percent).
Stage 2: Exercising the option and the S&P (April to June 2026)
Within three weeks of the option date, buyers exercised by signing the Sale and Purchase Agreement and paying 15 percent (less the booking fee already paid, under the normal scheme). Stamp duty fell due within 14 days of exercise. HDB's eligibility check is repeated at this stage.
What to keep: the signed S&P, the option, the stamp duty certificate, and the developer's letters. They are the documents a bank, HDB or a future buyer will ask for.
Stage 3: Construction and progress payments (2026 to 2030)
Under the Normal Payment Scheme, the 80 percent balance is paid in stages tied to construction milestones: foundation, reinforced concrete framework, brick walls, ceilings and roofing, electrical wiring and plumbing, car park and roads and drains, and then TOP. Each stage is certified by the architect and the developer sends a notice; the bank disburses the matching loan tranche and the buyer starts servicing it.
Under the Deferred Payment Scheme nothing is payable during this period and no loan is drawn.
For bounce-unit buyers: a buyer who comes in during construction pays, on signing, every stage that has already been certified. Budget for it.
The progress page carries dated updates and photographs from the appointed marketing agency's site visits. The developer's own notices remain the authoritative record.
Stage 4: TOP and key collection (expected by 30 June 2030)
The Temporary Occupation Permit is issued by the Building and Construction Authority when the building is safe to occupy. Developers in Singapore routinely obtain TOP before the contractual vacant possession date; a contractual date of June 2030 for a project that began sales in March 2026 suggests the developer expects TOP in late 2029 or the first half of 2030 (an estimate, not a date).
At TOP the final construction stage payment (and, under DPS, the full 80 percent) falls due, the bank disburses, and the developer issues the notice of vacant possession. Owners then collect keys, usually by appointment over several weeks.
What to do at key collection: inspect the unit before signing the handover form. Bring a checklist: doors and windows, floor and wall finishes, bathroom fittings and water pressure, kitchen fittings, aircon operation, electrical points, the household shelter door. Photograph everything. Rivelle's brochure lists Samsung, Villeroy & Boch and Küche fittings and a smart home system (digital lockset, aircon control, lobby access); check each against the specifications in the S&P.
Stage 5: Defects liability period (12 months from vacant possession)
The developer is obliged to make good defects notified within the defects liability period, which for Singapore private residential developments is 12 months from the date of vacant possession under the standard S&P. Submit defects in writing to the developer, keep copies, and follow up. Items commonly reported at ECs: hairline cracks, hollow tiles, misaligned doors, grouting, and aircon drainage.
The MOP clock starts at TOP, not at key collection, so owners who collect keys three months after TOP have three months less of MOP to serve.
Stage 6: Management corporation and maintenance (from around 2031)
For the first year or so the developer manages the estate and collects maintenance fees. The management corporation (MCST) is constituted once the strata titles are issued, and owners elect a council at the first AGM. Rivelle's facilities list runs to 72 items including two lap pools, a tennis court and a three-level clubhouse; the sinking fund and the maintenance budget the first council sets will matter for the next decade.
Legal completion, when the developer delivers the strata title and the balance of the purchase price is settled, is contractually expected by 30 June 2033.
Stage 7: Minimum occupation period (TOP to around mid-2035)
The MOP for an EC is five years from the date of TOP. During the MOP an owner:
- must occupy the unit (the family nucleus listed in the application must live there);
- cannot sell the unit;
- cannot rent out the whole unit (renting a room is allowed once the owners have moved in);
- cannot buy another HDB flat or EC;
- may buy private property only after the MOP, with the usual 30-month rule applying in the other direction for anyone who later wants a new EC.
With TOP expected by 30 June 2030, Rivelle's MOP ends around mid-2035 (estimate). Owners who are planning to upgrade or relocate should work backwards from that date.
Stage 8: Resale to citizens and PRs (years five to ten, around 2035 to 2040)
After the MOP, a Rivelle unit can be sold on the open market to Singapore citizens and permanent residents, and rented out whole. Buyers at this stage need not meet the EC income ceiling or family nucleus rules; they do need to be citizens or PRs. Sellers who received CPF housing grants pay nothing back beyond the usual CPF refund with accrued interest; second-timers who later buy a subsidised flat pay the resale levy.
This is the window in which Aurelle of Tampines (TOP around 2028, MOP around 2033) and Tenet (TOP around 2026, MOP around 2031) will already be trading, and their prices will be the reference for Rivelle's first resale listings.
Stage 9: Privatisation (year ten, around 2040)
Ten years after TOP, an EC is fully privatised: it can be sold to foreigners and companies, exactly like a private condominium. For Rivelle that is around mid-2040 (estimate). Historically the discount of a resale EC to comparable private condos narrows as privatisation approaches, which is why the ten-year hold is the one most EC buyers plan for.
A summary table
| Stage | Date | Basis |
|---|---|---|
| Preview | 6 March 2026 | Owner-supplied, to be confirmed |
| Booking day | 21 March 2026 | Owner-supplied, to be confirmed |
| Sold out | 24 April 2026 | Owner-supplied, to be confirmed |
| Expected vacant possession (TOP) | 30 June 2030 | Contractual, brochure |
| Defects liability period ends | about 12 months after vacant possession | Standard S&P |
| Expected legal completion | 30 June 2033 | Contractual, brochure |
| MOP ends | around mid-2035 | 5 years from TOP, estimate |
| Privatisation | around mid-2040 | 10 years from TOP, estimate |
For future buyers
If you want a Rivelle unit and are not an owner today, you have two routes: a bounce unit during construction, or the resale market from 2035. If neither timing works, the executive condominiums now launching reach their own TOP and MOP a year or two before Rivelle; they are listed on the showflat page and in detail on singaporeec.sg. Owners who want the MOP and resale rules explained with examples will find them in singaporeec.sg's EC MOP and resale guide.